Identifying When a Project will be Completed
Projects are completed based on approval submission date or criticality.
Only campus administrators may approve a change of priority for staff or faculty submitted projects.
Use the link below to open the schedule for planned and requested projects.
Project Planning and Progress (requires MS Excel)
Depending on the scale of any project, time is required to appropriately carry out the work. The chart below is a general guideline of how much time a project may require before completion.
| Range of Duration for Projects UNDER $400,000 |
| Process |
Duration |
| Estimating and Scoping |
1-6 Weeks |
| Architect and Engineer Selection (unless in-house design) |
1-4 Weeks |
| Design and Specification |
1-13 Weeks |
| Bidding and Award |
2-8 Weeks |
| Construction, Occupancy and Closeout |
4-23 Weeks |
| |
|
| Range of Duration for Projects OVER $400,000 |
| Process |
Duration |
| Programming |
4-12 Months |
| Architect and Engineer Selection |
1-3 Months
|
| Design and Specification |
3-12 Months |
| Bidding and Award |
2-3 Months |
| Construction, Occupancy and Closeout |
3-36 Months |