Physical Plant—Project Priority

Identifying When a Project will be Completed

Projects are completed based on approval submission date or criticality.

Only campus administrators may approve a change of priority for staff or faculty submitted projects.

Use the link below to open the schedule for planned and requested projects.

Project Planning and Progress (requires MS Excel)

Depending on the scale of any project, time is required to appropriately carry out the work. The chart below is a general guideline of how much time a project may require before completion.

Range of Duration for Projects UNDER $400,000
Process Duration
Estimating and Scoping 1-6 Weeks
Architect and Engineer Selection (unless in-house design) 1-4 Weeks
Design and Specification 1-13 Weeks
Bidding and Award 2-8 Weeks
Construction, Occupancy and Closeout 4-23 Weeks
   
Range of Duration for Projects OVER $400,000
Process Duration
Programming 4-12 Months
Architect and Engineer Selection 1-3 Months
Design and Specification 3-12 Months
Bidding and Award 2-3 Months
Construction, Occupancy and Closeout 3-36 Months
Physical Plant Mission Statement

To create and offer services that contribute to a more pleasant way of life for students, faculty, staff, and visitors at Troy University wherever and whenever they come together.

U.S. Locations
International Locations
eArmyU
eCampus


Troy University, Troy, Alabama 36082, 1-800-551-9716, 1-334-670-3000
Read our Disclaimer | Website Feedback/Help | Questions?
© 2007-2008 Troy University