Action 1: Requestor delivers completed Project Request Form to Physical Plant
See Project Request on the menu to the left for hints and tips on filling out and submitting the form.
2 Physical Plant Provides Estimate and Schedule
Physical Plant project manager or estimator develops an estimated project budget based on typical materials and labor costs and previous University experience.
Physical Plant project manager establishes a tentative schedule for project start date.
The schedule will be in the form of SEM/YR.
Fall semester of 2006 is written as Fall/06.
Projects are scheduled on a "first-come, first-served" basis
See Project Priority for more information about project scheduling.
Action 2: Physical Plant returns estimate and tentative schedule to Requestor.
Senior Vice Chancellors, Executive Vice Chancellor, and Vice Chancellors (for cost centers under his/her
control)
$5,001 - $20,000
Executive Vice Chancellor and Senior Vice Chancellors
$20,001 - $30,000
Chancellor
Unlimited
Any project that alters the usage of a space requires approval from the Sr. Vice Chancellor for
Administration or
Sr. Vice Chancellor of Finance and Business Affairs.
Action 3: Requestor delivers authorized Budget Approval Form and Project Request Form to the Physical Plant.
4 Physical Plant Obtains Quotes/Estimates
Project manager is assigned to project.
Project manager obtains quotes and estimates.
Projected project costs.
A project with a projected cost of over $50,000 requires a publicly advertised bid. Alabama law prohibits projects that normally exceed $50,000 from being split into smaller projects to avoid the bid process.
A project with a projected cost of less than $50,000 is delivered or shown to three (3) or more contractors for bids.
In all cases, the lowest qualified bid is accepted.
Action 4: Physical Plant returns quotes to Requestor for Purchase Order (PO) generation. For Physical Plant approved, planned, and reserve-funded projects, Physical Plant generates the purchase order.
5 Requestor Obtains Purchase Orders
Requestor obtains purchase order (PO) according to individual department standards.
Action 5: Requestor returns purchase order (PO) to Physical Plant.
**Important** Before any project may commence, a purchase order must be successfully processed and a copy obtained by the project manager.
6 Work Commences
Physical Plant project manager submits Notice to Proceed to the selected company/contractor with a copy of the purchase order (PO).
Company/contractor returns finalized schedule, including start date and date of substantial completion.